MMRDA completes 73% of station works for Metro-5 line in Thane

Mumbai, Aug 2 : The MMRDA has completed erecting all precast elements for the six stations on the first phase of Metro-5 line from Thane to Bhiwandi in Thane district, a top official said here on Wednesday.

This includes 1098 station elements like spines, wings, U-girders, pier arms, L-beams, etc, thereby, achieving 73.

35 per cent of all the stations work on this corridor.

Besides, the work on 9.87 kms of a total 11.88 kms (80.50 per cent) viaduct elevated stretch comprising the six stations is also done, said Mumbai Metropolitan Region Development Authority Commissioner Dr.Sanjay Mukherjee.

Being built at a cost of Rs 8,416-crore, the Metro Line 5 is an elevated 24.9 kms stretch linking Thane-Bhiwandi-Kalyan towns in Thane district, of which the Phase I comprises 11.88 kms between Kapurbawadi in Thane to Dhamankarnaka in Bhiwandi.

ఆ ముసలి నక్కా అతనేనా హరీషా...పూర్తిగా చెప్పే దమ్ము లేదా ?...

The six stations en route are Balkumnaka, Kasheli, Kalher, Purna, Anjurphata and Dhamankar Naka and the unique aspect is the 550-metre long viaduct on the Kasheli Creek section plus traversing through the rural areas of Bhiwandi between Kasheli-Anjurphata.

After the precast elements work, now other aspects like flooring, fall-ceiling, facades, roof, laying tracks and system works will be taken up simultaneously to complete it within the stipulated deadline, said Dr.Mukherjee.